SYMPOSIA PAPER Published: 29 July 2019
STP161120170157

Mobilized Resistances Based on Static, Dynamic, and Numerical Methods at the Jingi Jingi Creek Bridge Replacement Project, Queensland, Australia

Source

The foundations of a 17- by 10-m span bridge that were used to replace a 145-m-long culvert on the Warrego Highway, west of Brisbane, Australia, have recently been completed. The bridge foundations consisted of 5- by 550-mm octagonal prestressed concrete (PSC) piles at the abutments and pier locations. A total of 90 PSC piles were installed. Prior to installing the production piles, three test piles were driven to nominal refusal per Queensland Department of Transport and Main Roads (QDTMR) guidelines. The test piles were dynamically tested using the Pile Driving Analyzer, and the activated (mobilized) resistances and their distributions were checked against those predicted from static- and finite element–based approaches. During the installation of the production piles, representatives of the piles were equally tested per QDTMR guidelines, and all results from the various methods at different stages of the project were analyzed and compared.

Author Information

Ezeajugh, Lambert, E.
Ground Environments Pty. Ltd., AU
Vanderstaay, Lex, G.
Queensland Dept. of Transport and Main Roads, AU
Price: $25.00
Contact Sales
Related
Reprints and Permissions
Reprints and copyright permissions can be requested through the
Copyright Clearance Center
Details
Developed by Committee: D18
Pages: 611–625
DOI: 10.1520/STP161120170157