ASTM WK39155

    Revision of C12 - 09 Standard Practice for Installing Vitrified Clay Pipe Lines

    (What is a Work Item?)

    Active Standard: C12 - 17

    Developed by Subcommittee: C04.20 | Committee C04 | Contact Staff Manager



    WK39155


    Keywords

    backfilling; bedding; clay pipe; compaction; construction; design; excavation; installation; load factors; perforated pipe; pipe; sewers; trench foundation; trenching; vitrified; Vitrified clay pipe/fittings; Backfill; Bedding; Clay pipe/piping systems; Compaction control; Construction; Design--piping systems; Excavation site; Leachate drainage; Trenches; Underground installation;

    Rationale

    Section 6.6.2 and 6.6.7 needs revision. Space along the side of the pipe needs to be filled with CLSM to achieve strength.

    Citing ASTM Standards
    Back to Top
    Work Item Status

    Date Initiated:
    09-25-2012

    Technical Contact:
    Mark Bruce

    Status:
    Approved