STP1129

    Effects of Construction of a Diaphragm Wall Very Close to a Masonry Building

    Published: Jan 1992


      Format Pages Price  
    PDF (204K) 12 $25   ADD TO CART
    Complete Source PDF (9.1M) 12 $55   ADD TO CART


    Abstract

    Observations were made to study the settlement behavior of an old 4 story masonry building during the construction of a 25m deep diaphragm wall. The adjacent building, which was only 1.2m to 1.5m from the wall, was supported on shallow footings founded on weak deposits of loose sand and soft clay. A preliminary assessment before construction in the critical area indicated that settlement would be excessive if conventional construction procedures were followed. This led to the adoption of several settlement control measures in the construction process. It was found that these measures were effective in restricting the average settlement of the adjacent building to only 7.2mm and there was no visible sign of cracking.

    Keywords:

    diaphragm wall, construction, control measures, building, settlement


    Author Information:

    Chan, SF
    Technical Director, Pilecon Engineering, Kuala Lumpur,

    Yap, TF
    Marketing and Contracts Manager, Bachy Soletanche, Kuala Lumpur,


    Paper ID: STP19728S

    Committee/Subcommittee: D18.20

    DOI: 10.1520/STP19728S